How Long Does a Fence Installation Actually Take?

From first call to finished fence, with the parts nobody warns you about — the 811 wait, material lead times, and the concrete cure.

Two to four weeks from first call to finished fence for a typical residential job, of which only one to three days is crew time on site. The rest is the 811 utility locate (two to three business days), material lead time, and scheduling.

Published 2026-08-16 · Updated 2026-08-16

The honest timeline

For a typical residential fence in the Jerome area:

Stage Time
Call to on-site estimate 2–3 business days
Estimate to written quote Same visit
Quote accepted to scheduled start 1–3 weeks, seasonal
811 utility locate 2–3 business days (runs in parallel)
Material lead time 0–2 weeks by material (parallel)
Crew on site 1–3 days
Concrete cure before gates hang 24–48 hours

Two to four weeks end to end, and only a few days of that is anyone in your yard.

That gap between “the crew is here for two days” and “this takes a month” is the single most common source of frustration, which is why it is worth setting out plainly.

What takes the time

The utility locate — unavoidable

Two to three business days, free, legally required, and not compressible. Any contractor offering to start tomorrow on a job needing a locate is telling you they intend to skip it. See calling 811 before a fence goes in.

Material lead time — depends what you chose

Stocked, usually no wait: wood, chain link.

Made to order, one to two weeks: vinyl, aluminum, ornamental steel. These come in your profile, color, and height, so nothing ships until the order is placed. Worth knowing when you are choosing material against a deadline.

The season

Fencing is intensely seasonal here. Spring through early autumn is busy, and lead times to a start date stretch accordingly. Late autumn and winter are quiet — the work is harder in frozen ground, but you will get on the schedule far faster and sometimes at a better price.

If your timing is flexible, booking in the off-season is the easiest saving available on a fence.

Concrete

Posts need to set before panels and gates load them. Usually an overnight wait, longer in cold weather. On a two-day job this is why gates hang on day two rather than day one.

What makes a job take longer

Removing an old fence. Add most of a day. Extracting old concrete footings properly — rather than snapping posts at grade — is real work, and it is worth the time.

Rock. Jerome County sits on basalt under three to ten feet of loess. A lot where rock is twenty inches down needs a rock auger or breaker, and holes that would take minutes take considerably longer. This is why we check soil at the estimate rather than discovering it on install day. See how deep posts need to go.

Slope. Racking panels to follow grade takes longer than building on the flat.

Gates. Every gate needs oversized posts, deeper footings, and hanging and adjustment time. A fence with four gates is a meaningfully longer job than the same footage with one.

Weather. Saturated ground and hard frost both stop post setting.

What we do to keep it moving

The locate gets filed as soon as you accept the quote, so it runs while material is ordered rather than after. Soil gets checked at the estimate, so rock is priced and planned rather than discovered. And we tell you the realistic start date rather than the one you want to hear — being honest about a three-week wait beats promising one week and delivering three.

If you have a hard deadline — a dog arriving, a pool inspection, livestock coming — say so at the estimate. Sometimes we can sequence around it, and where we cannot, you should know that before you commit rather than after.

Estimates are free across Jerome and the Magic Valley, usually within two business days, three for the Mini-Cassia towns.

The bottom line

If you want this priced for your own property rather than in ranges, we come out and measure at no charge across Jerome and the Magic Valley. You get a written per-foot price with gates and removal broken out separately. Call (208) 732-2816.

Questions

Quick answers

How long does a 150-foot fence take to install?

One to two days of crew time for most materials once everything is on site. Wood and chain link often go up in a single day; vinyl and aluminum can take longer because panels must be set to exact post spacing with no room to fudge. Gates and final adjustment usually account for the second day.

Why is there a wait before you start?

Two things run in parallel. The 811 utility locate takes two to three business days and cannot be compressed. Made-to-order materials — vinyl, aluminum, ornamental steel — have their own lead time from the supplier. Wood and chain link are usually stocked, so those jobs start sooner.

Can a fence be installed in winter here?

Often yes, though frozen ground makes augering slower and harder, and concrete needs cold-weather handling to cure properly. What genuinely stops work is deep frost or saturated ground. Winter jobs are sometimes cheaper because it is the quiet season — worth asking about if your timing is flexible.